What is Retention Money in Construction Contracts

Retention Money in Construction Contracts

If you work related to construction sector, then you know that retention money is one of the popular terms used in any construction project. However, do you know what is retention money in construction contracts? And do you know how to deduct it in progress payments?

For most quantity surveyors and contract engineers; deducting retention money is not any difficult task. They understand it clearly. However with experience working with contractors, I have found that some contractors do not understand the entire purpose of retention money in their projects. Even there are times that subcontractors do not submit their final claim to request the release of retention money.

While these are common issues found in construction project payments, some contractors do not clearly understand the reason why their payment is less than their actual progress claim.

Having worked in such different situations and having experience with solving issues arise related to retention money payment and deductions, in this article I want to share most of the theories and industry practices related with retention money.

Popular terms related to Retention Money

Before discussing further, it is important to understand the different terms used related to retention money. All these terms doesn’t mean the amount of retention to be deducted. Each term has its own definition.

What are the terms used in related to retention money? Let’s discuss!

The amount of retention money, limit of retention, release of retention are some of the common terms and activities involved in any construction project under this topic. Release of retention involves 2 different stages. That is First release of retention and 2 nd release of retention.

However there are times which we find that these terms or the actual purpose of retention money are misunderstood.

Although the amount of Retention Money can be different from contract to contract (due to the conditions of contracts used), the terms serve the same meaning to any construction project around the world.

In such, here is a brief of what is Retention Money in Construction contracts and how do you deal with it as a Contractor ,Quantity Surveyor or as a Contracts Engineer.

Warning: before reading further, you understand that these are guidelines only. You have to refer your actual conditions of contract to understand the specific percentages and clauses related to retention money.

Retention Money in Construction Contracts

What is Retention Money in Construction Contracts?

Retention money is described as the sum of money held by the employer as a safeguard for any defective or non-conforming work by the contractor. This provision safeguards the employer by defects which can occur during the defects liability period if the contractor doesn’t response according to the contract terms.

Purpose of Retention Money

In general, Retention Money provides protection to the employer. Retention money gives the idea of importance of completing the signed project as per it’s terms and designs. Contractor has to complete the scope of work under his contract in order to receive the retention money amount withheld.

This is how employer is protected against the money he pays in monthly progress claims.

With such retention held, the contractor takes the responsibility to complete the construction project as per the design and quality stated in the initial contract.

How to deduct Retention Money from the progress claim?

deduct Retention Money from the progress claim

In most of the construction contracts, the amount of Retention Money to hold in each progress claim is 10% of the work done and up to 5% of the contract sum.

However these figures can be different from contract to contract. Therefore you may need to refer the contract document for the construction project that you work before deducting any amount.

Here is how to deduct retention money from the progress claim.

The sum due to Interim Payment Certificate shall be calculated at the rate of 90% for the value of work done & at the rate of 80% for the properly protected materials or goods delivered on site. (Generally)

Therefore the percentage of the sum not paid is known as ‘Retention Money’ for the contract.

What is the ‘Limit of Retention Money?

Retention sum is subjected to limit as per the stated percentage in the contract which is known as ‘Limit of Retention’.

In general, ‘Limit of Retention’ is 5% of the contract sum. Therefore once the Limit of Retention is reached, you cannot deduct further Retention Money. In the subsequent interim certificates, you can see the total retention money deducted. However there will not have further deductions.

Release of Retention in Construction Contracts

Release of retention is another important term or milestone in any construction contract which is also an indication of completion of the scope of the project up to the mentioned stages.

Usually, retention monies are released in 2 stages of the project.

1. Release of the first half of the Retention Monies

at the time of issuing the Completion Certificate, The first half of the Retention Monies will be certified and released

If there is any outstanding work for the project, those will be stated in the Completion Certificate.

If there are outstanding work available and if the contractor doesn’t accept to complete such rejected work or any outstanding work, QS can deduct a reasonable amount for completing such remaining work.

This reasonable cost will be the amount of money to cover the costs of completing the remaining work by engaging a 3rd party.

2. Release of the second half of the Retention Monies

The second half of Retention Monies will be certified and released upon the expiry of defects liability period. In most construction contracts, the Defects Liability period is 12 months which the contractor is liable to complete any defects arise due to the poor workmanship.

Upon issuance of Maintenance Certificate, the 2nd half of Retention Money will be released.

Important things to know

As a contractor or QS in charge for a project, below are the mistakes and misconceptions to note.

Above are the basic concepts behind the term ‘retention money in construction contracts’. Usually project QS or engineer who deals with the progress payments know most of these details.

If you find this post is helpful, please share your thoughts.Also read this post about variations in construction contracts.